About the work of Novovoronezh NPP in Mar 2007



06.04.2007 // Press service of Rosenergoatom

In Mar 2007 Novovoronezh NPP produced 1.027bln KWh – 86.9% of the plan

The low production was due to the stoppage of the 5th unit on Mar 11–17 and the 4th unit on Mar 24–29 (see Mar 13 and Mar 22 reports).

The 3rd, 4th and 5th units are working according to the plan.

The capacity factor made up 75.4% with the plan being 86.7%.

No safety limits were exceeded.

The radiation emission was within controlled limits:

The average radiation background in the settlements of the 30km zone was within norm – 8–25 mR/h:

Index

Neutral radioactive gases

Iodine-131

1

2

3

Monthly emission in % of admissible level

5.4 %

4.3 %

 

The average radiation background in the 30km zone
01.03.2007–31.03.2007

¹¹

 

Name of settlement

Average monthly index (mR/h)

 

1.

Anoshkino

8.1

2.

Arkhangelskoye

9.4

3.

Boyevo

11.4

4.

Borschevo

11.5

5.

Kamenno-Verkhovka

8.2

6.

Kostenki

9.3

7.

Krugloye

9.0

8.

L.Rossosh

8.4

9.

Mastugino

8.2

10.

Novovoronezh

9.8

11.

Oskino

10.4

12.

Storozhevoye

9.5

13.

Yablochnoye

10.9

14.

Shilovo

10.4

15.

Voronezh

12.0


 