30.08.2007 // Information Department of Novovoronezh NPP
Turbine generator 9 of unit 3 of Novovoronezh NPP was restarted on Aug 29 11:46 PM after repairs
The unit was stopped on May 22 for 40-day planned preventive repairs. However, during the repairs the personnel detected a problem that required more time: cracks in the welded joints of steam generator 1.
It was the first time such a problem had occurred at an NPP. It required new technique and expertise of research companies. As a result, the period of the repairs was extended.
Presently, unit 4 of Novovoronezh NPP is operating at full capacity, unit 5 is under repairs, turbine generator 10 of unit 3 is being prepared for restart.