25.01.2008 // Information Department of Kalinin NPP
Unit 1 of Kalinin NPP was restarted on Jan 2008 at 3:12 AM
The unit was stopped for 24-hour repair on Jan 24 2008.
The repair is over and, presently, all the three units of the plant are in service.
As of 9:30 AM, the capacity of unit 1 made up 926MW and was being raised. The capacity of unit 2 was 1040MW, unit 3 – 1015MW.
The radiation background at the plant and in the monitoring zone is within norm.